▽ +09.00Technical detail · PS-D-02

Internal corner

A wall–floor internal angle: fillet, primer, a reinforcing strip embedded in the first coat and two continuous coats.

+01.00PS-D-02

Section and numbered callouts

PS-D-02 Internal corner — typical section1. Wall (concrete, or rendered blockwork) · 2. Wall finish: tiles on flexible adhesive · 3. Second coat, continuous over both faces · 4. Reinforcing strip embedded in the first coat · 5. First coat of liquid-applied membrane · 6. Primer, as the system requires · 7. Mortar fillet or cove · 8. Movement joint in the tiling, flexible sealant · 9. Floor tiles on bedding mortar · 10. Screed to falls · 11. Concrete slabFFLFFL + hFALL617253489101102PS-DNTS
PS-D-02SectionNTSR0 · 2026-10-08Typical detail — not for construction

Callouts

  1. 1Wall (concrete, or rendered blockwork)الجدار (خرسانة أو بلوك مُليّس)
  2. 2Wall finish: tiles on flexible adhesiveتشطيب الجدار: بلاط على لاصق مرن
  3. 3Second coat, continuous over both facesالطبقة الثانية متصلة على الوجهين
  4. 4Reinforcing strip embedded in the first coatشريط تقوية مدمج في الطبقة الأولى
  5. 5First coat of liquid-applied membraneالطبقة الأولى من العزل السائل
  6. 6Primer, as the system requiresبرايمر حسب النظام
  7. 7Mortar fillet or coveفيليه أو زاوية مقوسة من المونة
  8. 8Movement joint in the tiling, flexible sealantفاصل حركة في البلاط بمانع تسرب مرن
  9. 9Floor tiles on bedding mortarبلاط الأرضية على فرشة مونة
  10. 10Screed to fallsصبة ميول
  11. 11Concrete slabالبلاطة الخرسانية

Technical review

Need this detail on your project?

Send your drawings, penetrations and joints; our technical team reviews them and proposes the right detail for the approved system.

Ask Prime Shield Engineer

Connecting…

The assistant’s answers are guidance based on Prime Shield’s published content; the final technical decision follows a review by a Prime Shield engineer.

Call us+966 59 240 0524 E-mail uscontact@primeshield.com.sa